Project
25 November 2026
KAS Scaffolding Ltd was engaged to design, supply, and erect a specialised industrial access tower at Eurovia PolyBitumens to facilitate the installation of a new gas line. The four-week package centred on a 24-metre-high access tower (approximately 3m x 2.4m) built to the middle gantry, stepping onto an existing staircase and extending a further 8 metres to reach the top level of the industrial plant.
Erecting a high-level access structure around an industrial processing plant presented intricate spatial and structural hurdles. The tower had to be constructed under, around, and directly off existing steel staircases and gantries, requiring the scaffold to cantilever out and change direction to navigate the building's steelwork. Crucially, pedestrian access onto the existing staircase had to be maintained throughout the works. Additionally, the working lifts—boarded at 3-metre intervals—required a precise 600mm x 500mm void left within the inside boards to allow the new gas pipework to rise vertically through the structure, introducing a fall risk that demanded strict edge protection.
To safely navigate the plant's structural constraints, KAS Scaffolding delivered a fully engineered design package, progressing from preliminary approval drawings to finalised construction drawings backed by structural calculations and an independent CAT 1 check. The cantilevered tower was securely tied to the underside of the existing staircase steels and main building protrusions in accordance with NASC TG4 guidance, whilst the first fully boarded platform was erected at 4 metres—double-boarded with a netting insert to comply with SG34 protection standards above the live access route. The 600mm x 500mm pipework gap was fully handrailed off to eliminate fall hazards, and two elevations were clad in Monarflex sheeting in strict compliance with TG27. Complete with gated ladder access and four weekly inspections, the structure provided a secure 1.5kN/m² working platform. By combining intricate cantilevered engineering with strict NASC compliance, KAS Scaffolding delivered a safe, adaptable industrial access solution that enabled critical utility works without disrupting site access.
Work with us